Sample content

Move permit intake online by March

Most permit applications wait in the counter queue, not in review. Taking them online removes the wait without adding reviewers.

In October the counter took 1,184 applications. The median applicant waited 47 minutes to hand in a form that a reviewer then opened 3 days later. Review time has held steady for a year; the queue has grown every month since May.

Online intake moves the form, the fee, and the document check to before the visit. Applicants who submit online skip the queue entirely. The counter stays open for people who need help filling the form in.

Why March

The spring building season starts in April and October's volume doubles by May. Launching in March gives four weeks to fix problems before the peak.

What changes

StepNowAfter March
FormPaper, at the counterOnline, before the visit
FeeCard or check at the counterCard online
Document checkClerk, during the visitAutomatic, with a list of what is missing
CounterEvery applicantApplicants who ask for help

Cost

The intake form runs on the records system the office already licenses. The one new cost is the payment processor's fee.

Counter staff move to the help line and the document check for paper applications, so no position changes.

Setup
$18,400 one time
Payment fees
$2.10 per online permit
Counter cost now
$9.80 per permit
Break-even
About 2,400 online permits

Risks

  • Applicants without a card still need the counter. It stays open with the same hours.
  • Wrong uploads move the delay to review. The automatic check lists missing documents before payment.
  • The records system vendor needs six weeks' notice for the form. Notice has to go out by January 20.